< All projects
Leman Street
Description
The job is a 24 storey groundworks and RC frame package for Bennett Construction in E1.
Construction Features
- GCL precast columns
- 7 day turnaround of floors
- 1metre deep transfer slab
- Peri (CB240) platforms used in order to construct shear wall
- Radius slab on all 24 floors
Innovation
- Precast elements prefabricated off site at GCL precast yard Luton in order to speed up construction time
- Temporary works by GCL technical department